Company: Various
Length: November 2018 - December 2020
Services provided:
Providing back office design engineering support to various Design Consultants for Overhead Transmission Line (33kV to 230kV) and Substation (Civil & Structural) Projects North East USA.
Company: Various
Length: November 2018 - December 2020
Services provided:
Providing full GIS services and LiDAR Data Processing, Drone data/photos classification, processing and record keeping for asset management for Overhead Transmission and Distribution Lines (33kV to 230kV) in East Coast USA.
Company: Exelon-Pepco Holding inc
Length: November 2018 - December 2020
Services provided:
Various projects for rehabilitation of 33kV, 69kV, 138kV, 230kV and 500kV overhead transmission line networks. Condition assessment, site survey to collect data, refurbishment, diversion, line entry, up rating, reconductoring and new line design.